BILDIRIM ICERIGI
ACIKLAMALAR
ACIKLAMA
OZGUN GIDA SANAYI VE TICARET
LIMITED SIRKETI (OZGUN GIDA, YUKLENICI) ILE 20 ARALIK 2013 TARIHINDE SATIS VAADI VE
ARSA PAYI KARSILIGI INSAAT SOZLESMESI IMZALANMISTIR. YUKLENICI,DAIRELERI SOZLESMEYE
GORE INSAAT RUHSATLARININ ALINDIGI
TARIHTEN ITIBAREN 36 AY ICINDE TESLIM EDECEGINI TAAHHUT ETMISTIR.
INSAAT RUHSATLARI 07.07.2014
TARIHINDE ALINMIS VE GEREKLI INSAAT IZINLERI VE ISKÂN CIKARILMA ISLEMLERI 2014 YILI ICERISINDE TAMAMLANMISTIR. FIILI
INSAAT OZGUN GIDA TARAFINDAN 2014 YILI SONUNDA BASLATILMISTIR.
BU ITIBARLA, INSAATLARIN TESLIM
SURESI 07.07.2017 OLARAK KABUL EDILMISTIR.
OZGUN GIDA TARAFINDAN INSAATLARIN
GELISIM SURECI ILE ILGILI OLARAK INSAAT SURECININ NORMAL SEYRINDE DEVAM ETTIGI
VE BILDIRILMIS VE ASAGIDAKI ACIKLAMA GONDERILMISTIR.
INSAATLARIN GELISIM SURECI, INSAATIN
TAMAMLANMASI VE TESLIM ALINMASINA KADAR OZGUN GIDA TARAFINDAN EN GEC 2 AYDA BIR
GUNCELLENECEK VE SIRKETIMIZ TARAFINDAN
KAP’TA ACIKLANACAKTIR.
INSAAT GELISIM SURECI
KABA ISLER
KABA INSAAT KISMININ
BODRUM+ZEMIN+20 KAT BLOK KISMININ TAMAMI TAMAMLANMISTIR. BODRUM OTOPARK
KISMININ TEMEL CALISMALARINA
BASLANMISTIR VE BAZI CEPHELERININ TEMELLERI DOKULMUSTUR VE CALISMALARA
DEVAM EDILMEKTEDIR.
INCE ISLER
CEPHE VE ARA BOLME
DUVARLARININ %95 INE YAKINI VE ALCI SIVANIN %90’INA YAKINI TAMAMLANMISTIR. CATI
TERASLARININ IZOLASYONU, TOPUK
BETONLARI, ISLAK HACIMLERIN KARA SIVASI ,ASMA TAVAN UYGULAMASI VB
MUHTELIF INCE ISLER
IMALATLARINA BASLANMIS VE CALISMALARI DEVAM ETMEKTEDIR.
MEKANIK ISLERI
MEKANIK ISLERE AIT YANGIN,
ISITMA VE SIHHI TESISATLARA AIT IMALATLAR DEVAM ETMEKTEDIR.
ELEKTRIK ISLERI
ELEKTRIK ISLERINE AIT KABLO
TAVALARI, KABLO CEKIM ISLERI VE DAIRE SIGORTA MONTAJLARI TAMAMLANDI. ASANSOR
KUYU AYDINLATMA VE YANGIN ALGILAMA
TESISATLARININ MONTAJINA DEVAM EDILMEKTEDIR.
CEPHE ISLERI
CEPHE ISKELELERININ KURULUMU
DEVAM ETMEKTEDIR. ISKELE MONTAJININ %85 INE YAKINI TAMAMLANMISTIR.
MONTAJDAN SONRA GIYDIRME CEPHE
ANKRAJ VE PROFIL MONTAJLARINA BASLANACAKTIR.
ASANSOR ISLERI
ASANSOR MONTAJI CALISMALARINA
BASLANMISTIR. ASANSOR KUYU RAYLARININ MONTAJ CALISMASI DEVAM
ETMEKTEDIR.